Client

CrossBoundary Energy

Location

Lari, Kiambu

Duration

3 weeks

Project Description

The project scope of works entailed project planning; Establishment of permanent benchmarks (BMs); Conducting Planimetric survey within the provided site boundary; executing Altimetric survey with 0.25m contour lines, showing line breaks and other breaking points as required; Identification and measurement of any permanent landmarks within the proposed construction area, including but not limited to; powerlines, pylons, houses, wells, rivers, protected trees, swampy areas, internal paths, gas pipelines, telecommunications lines, large vegetation areas, infrastructure, towers, drainage, roads, boreholes, along with any other notable features considered relevant to construction. DataĀ processing using AutoCAD Civil 3D and ArcGIS Pro software to generate the topographical maps, cross-sectional and longitudinal profiles, plans and reports.

Categories
  • Topo Survey
  • Stonex
  • GNSS
AGM Magazine

AGM Magazine